Project 2 – Building Progress & photos Click on photos to enlarge Weeks 6, 7, 8 All house foundations dug and concreted Enough blocks on site for the brickies to start Site compound with foundations of houses 1,3 &5 underneath Weeks 4 and 5 lots of foundation work Bungalow footings dug Lower road marked out When these Maisonettes are complete there will be grass, not mud Week 3 beginning Mark Out Big kit on site and the temporary mess hut Topsoil cleared and three-quarters of clay Marking out foundations of plots 29,30 and 31 Week 2 – scraping off and building the acoustic bund 80% of acoustic bund already REALLY big machines First evidence of work starting