May – first Timber Frame as per the videos
This Drone Shot shows the anti-clockwise sequence of building, from the two-bed semi being worked on by the crane, with the base for the pair of Maisonettes next (scaffolding arrived for that on 22nd May)
(credit Jason Key)
May – Sequence of build from foundations to ground floor complete
Weeks 6, 7, 8 All house foundations dug and concreted
Weeks 4 and 5 lots of foundation work
Week 3 beginning Mark Out
Week 2 – scraping off and building the acoustic bund
First evidence of work starting